What additional liability does a contractor face when a fixed-price contract is terminated for default?

Prepare for the Contracting Officer Warrant Board (COWB) – Unlimited Warrants Test. Utilize comprehensive multiple choice questions and supportive explanations to enhance your understanding and readiness.

When a fixed-price contract is terminated for default, the contractor faces the liability of reimbursing excess costs incurred by the government. This is because, in the event of a default termination, the government can choose to obtain the goods or services from another source. If the costs associated with this replacement are greater than the contract price, the contractor is responsible for covering the additional expenses incurred.

This provision serves to protect the government from financial losses resulting from a contractor's failure to fulfill their obligations. It reinforces the expectation that contractors must perform according to the terms of the contract, as their failure to do so can have financial repercussions, specifically impacting their liability to reimburse for any excess costs when the government has to seek alternatives to fulfill its needs.

In contrast, while performance bonds are often associated with certain contracts to protect against default, they do not create additional liability in the event of termination. Any potential early termination penalties are not typically applicable to the contractor in this situation, as those generally pertain to the government's responsibilities. Additionally, the ability to claim loss of profits on future contracts is not a result of a termination for default; rather, it would typically relate to a different context in contract disputes. Thus, the correct understanding revolves around the contractor's obligation to

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy